On November 12, the Minneapolis City Council voted 7-6 to approve an ordinance that steers new data centers into existing downtown buildings. The Daily Caller reported that the final version limits them to two downtown overlay districts and requires council approval for each new project. The ordinance now sits with Mayor Jacob Frey, and the city's six-month moratorium on most new data centers expires November 21.
The context matters. According to FOX 9, downtown Minneapolis already has eight data centers, council members said Xcel Energy has reported interest in up to eight more downtown projects, and city staff said 30 percent of downtown stands empty. Supporters on the council argued that data centers could fill vacant downtown space and boost the property tax base. Opponents pushed for a full ban, which failed.
What the ordinance requires
Based on reporting from KARE 11, FOX 9 and the Daily Caller, the version the council passed:
- Allows new data centers only in existing buildings, which the Daily Caller reports means buildings that existed as of January 1, 2027
- Requires the building to have at least one other main use; the data center cannot be the primary use
- Keeps servers off the first and second floors
- Requires servers to sit at least 100 feet from nearby homes and 20 feet from exterior walls
- Caps server space at 50,000 square feet, or 150,000 square feet for operators that join an Xcel Energy renewable program and pay a premium for renewable energy credits
- Requires disclosure of expected energy, water and generator use, plus a sound attenuation plan and a decommissioning plan
What happens next is still open
Frey's office has said he supports the compromise's "regulatory framework." Before the final vote, MPR News reported council members saying Frey would veto a full ban or an overlay district requiring council approval for each data center, a provision that was added before passage. Overriding a veto takes nine votes, and the ordinance passed with seven. MPR also reported that if no new rules are in place when the moratorium expires, existing zoning applies, which allows data centers with a permit in 10 of the city's 15 zoning districts. The council meets again November 20.
The final shape of the rules may change this week. The questions they raise will not.
Why this matters beyond Minneapolis
Much of the data center debate centers on large greenfield campuses. Minneapolis wrote rules for a different product: data space on the upper floors of a mixed-use building, inside a downtown with a lot of empty office space. Owners of underused office and industrial buildings in other cities are looking at the same opportunity. Whether or not their city adopts similar rules, these are the questions a conversion has to answer.
1. Can the building carry data space above the second floor?
Keeping servers off the first two floors moves the heaviest equipment up the building. That puts floor loading, slab-to-slab height, freight elevator capacity and vertical shafts for power and cooling at the top of the list. Many office buildings can support data space on some floors and not others, and the answer comes from the structure, not the rent roll. We walk through the building-level checks in Reading a Building as a Data Center.
2. Does the rest of the building still work?
If the data center cannot be the primary use, the owner is planning a true mixed-use asset. That raises practical questions about shared lobbies and loading docks, security separation, generator placement, and noise and vibration near office or residential tenants. A leasing plan for the remaining floors belongs in the feasibility study, not after it.
3. How big can the data space be, and what does the power cost?
In Minneapolis, the difference between 50,000 and 150,000 square feet of server space depends on joining a renewable program and paying a premium. Every market has some version of this question: how much capacity the utility can deliver to the building, on what timeline, and at what full cost. Those answers set the size of the project, and they belong in the base case of the financial model.
4. How much usable floor is left after setbacks?
A 20-foot setback from exterior walls takes a meaningful share of a typical office floorplate out of play for servers. Add a 100-foot separation from nearby homes, sound attenuation and generator disclosure, and the usable data space on a floor can be far smaller than the gross area suggests. Test fit layouts early, floor by floor, before anyone commits to a capacity number.
5. Is the approval path in the schedule?
Case-by-case council review, disclosure of energy and water use, and a decommissioning plan all take time and preparation. In a city where nearly half of about 1,600 written comments asked for an outright ban, according to MPR News, approval is a schedule item, not a formality. Projects that arrive with clear figures on power, water, noise and tax revenue give a council something concrete to evaluate.
MDI Access helps owners evaluate whether an existing building can host data center space, size the opportunity against real power and approval constraints, and manage adaptive reuse projects through delivery as an independent, vendor-neutral advisor.
Talk to one of our advisors about your building
Sources
- Samantha Fischer, "Minneapolis City Council agree on data centers and new protections, send plan to Mayor Frey," KARE 11 via Yahoo News, November 12, 2026: https://www.yahoo.com/news/politics/articles/minneapolis-city-council-set-vote-155044876.html
- Madison Hunter, "Minneapolis City Council approves data center ordinance, but fails to pass full ban," FOX 9 via Yahoo News, November 12, 2026: https://www.yahoo.com/news/politics/articles/minneapolis-city-council-approves-data-021202645.html
- Simon August, "Minneapolis Narrowly Votes To Make Big Data Centers Buy Green Power," Daily Caller, November 14, 2026: https://dailycaller.com/2026/11/14/minneapolis-data-center-rules-oakland-moratorium/
- Cait Kelley, "Data center regulations up for vote at Minneapolis City Council," MPR News, November 12, 2026: https://www.mprnews.org/story/2026/11/12/data-center-regulations-up-for-vote-at-minneapolis-city-council
- Emily Pofahl, "Minneapolis set to pass sweeping data center regulations," FOX 9, November 9, 2026: https://www.fox9.com/news/minneapolis-set-pass-sweeping-data-center-regulations